Overview:
This project involved the augmentation of a section of an existing recycled water main between Pimpama STP and Coombabah STP. The Work involves installing OD660 and OD800 diameter pipeline, approximately 1.65 km in total length.
Scope:
-
Service Investigations (in-house)
-
Clearing & grubbing
-
Supply & Installation of OD660 above-ground MSCL pipework
-
Supply & Installation of OD800 open-cut pipework through RAMSAR wetlands
-
Connections to the existing recycled water network
-
High level dewatering management
-
Acid sulphate soil management throughout the project